The State House
Home

About Montpelier

Area Attractions
& Things to Do


Doing Business
in Montpelier


Getting Here
& Getting Around


City
Departments
& Services
 
  • Welcome
  • Budget
  • City Assessor
  • Clerk / Treasurer
  • City Manager
  • Community & Economic Development
  • Finance
  • Fire & Ambulance
  • Montpelier Cemeteries
  • Justice Center
  • Parks
  • Planning & Development
  • Police
  • Public Works
  • Recreation
  • Schools

    Boards
    & Commissions


    Other Services
    & Organizations


    Calendar of Events

    News - Weather

    Notices -
    Jobs - Bids


    WHAT'S NEW

    Works in Progress

    Document Library

    U.S.S. Montpelier
    Museum




    Search the site...
    Budget
    Fiscal Year 2008 (FY08)
    July 1, 2007 to June 30, 2008
    Capital Improvement Plan
    Budget subsection links
    Budget Main Page~FY09  |  FY08  |  FY07  |  Contact Us
    FY08 Links 
    Manager's Budget Message
    General Fund - revenues
    General Fund - expenditures
    Water Fund
    Sewer Fund
    Parks Fund
    Cemetery Fund
    Parking Fund
    Equipment Plan
    Capital Improvement Plan
    Outside & Inside Agencies

    GENERAL FUND
    PROJECT BY FUND MASTER PLAN Funding Source FY07 - CITY COST FY08 - CITY COST FY09 - CITY COST FY10 - CITY COST FY11-
    CITY COST
    FY12-CITY COST FY13-CITY COST BONDED AMOUNT OTHER FUNDING: Outside, CDA, Fund Balance, E-VT, etc. After FY13 - CITY COST TOTAL PROJECT COST INCLUDING FINANCING COSTS, IF APPROPRIATE
    Class II STREET RESURFACING
    Barre Street (Charles-Granite)   CIP $36,000                   $36,000
    BarreStreet (Granite to Pioneer) Coordinate with Bike Path   CIP/State     $0 $30,000         $69,000   $99,000
    Berlin (River - City Line)   CIP/State   $0 $0 $30,000         $60,000   $90,000
    Main Street (Towne - City Line)   CIP/State     $0 $34,000 $30,000       $60,000   $124,000
    Class III STREET RESURFACING
    *See List of Streets of Possible Resurfacing SEE PAVEMENT STUDY-Current Overall Street Rating 75   CIP $113,878 $31,628 $19,205 $52,442 $61,819 $49,920 $191,741     ONGOING $376,082
    COMBINED SEWER OVERFLOW (CSO) RELATED RESURFACING Pg 53 CIP                   ONGOING $80,000
    SUBTOTAL STREET RESURFACING includes Sidewalks when required
        $149,878 $31,628 $19,205 $146,442 $91,819 $49,920 $191,741   $189,000 $0 $725,082
    *LIST OF STREETS - NOT IN PRIORITY ORDER
    Class III Street Resurfacing List: North Park Drive, Hebert Road, Isabel Circle, Loomis, Murray Road, Pitkin, Blanchard, Spring Hollow Lane, Msgr. Crosby, Woodrow, Corse, Pleasant, Dunpatrick, Freedom Drive, Cross Street (37) , Mechanic Street
    STREET REHABILITATION Reprofile & Resurface/Recycle
    CLASS II
    Towne Hill Road-Phase II(Grandview to City Line-See also Sidewalk Ext)   CIP/State $50,000 $80,000             $175,000   $305,000
    Gallison Hill Road-Bike Path   CIP/State   $0   $10,000             $10,000
    CLASS III
    Bliss Road   CIP         $30,000 $50,000         $80,000
    Grandview Terrace   CIP     $100,000 $0             $100,000
    Bailey Avenue (Terrace - Clarendon)   CIP $22,000                   $22,000
    Fuller Street-Council postponed project in FY 06   CIP   $39,000   $0             $39,000
    Deerfield Drive   CIP         $0   $80,000       $80,000
    Country Club Road   CIP                     $43,000
    Terrace (Bailey -No. 27)   CIP $19,000 $23,000                 $23,000
    Hubbard Park Drive   CIP           $114,000         $114,000
    Park Side Drive   CIP     $28,000               $28,000
    SUBTOTAL STREET REHABILITATION
        $91,000 $142,000 $128,000 $10,000 $30,000 $164,000 $80,000   $175,000 $0 $844,000
    STREET RECONSTRUCTION
    Lower State Street Reconstruction   CIP/State                 $720,000 $80,000 $800,000
    Elm Street (Vine-Pearl)   CIP/State                 $567,000 $63,000 $630,000
    Northfield Street Reconstruction   CIP/State                 $1,296,000 $144,000 $1,440,000
    Towne Hill Road (Road, Storm Sewer & Sidewalk)   CIP/State                 $1,782,000 $198,000 $1,980,000
    SUBTOTAL STREET RECONSTRUCTION
        $0 $0 $0 $0 $0 $0 $0   $4,365,000 $485,000 $4,850,000
    TOTAL ALL STREETS
        $240,878 $173,628 $147,205 $156,442 $121,819 $213,920 $271,741   $4,729,000 $485,000 $6,419,082
    BRIDGES
    Langdon St. Bridge Reconstruction Sidewalk improvements included(5%Local Share)C in FY 06 (See MDCA FY 06 Sidewalk contribution) Pg 30, 35 CIP/State C             $60,000 $1,140,000   $1,235,000
    Memorial Bike Path Bridge, Deck & Lights   CIP C C           $100,000     $115,000
    Vine Street Pedestrian Bridge Pg 35 CIP/State     D C       $160,000     $160,000
    Rialto Bridge Pg 30 Bond/State               $215,000 $1,935,000 C $2,150,000
    Cummings Street Bridge Replacement Pg 30 Bond/State               $100,000 $900,000 C $1,000,000
    North Branch Riverwalk (Pedestrian Walkway between Langdon/Rialto Bridges) FY04 $10,000 Study ($40,000 Grant for Study) C after FY 12 Pg. 35 CIP/Bond/State $0 $0 $0 $0         $40,000 $540,000 $590,000
    Taylor Street Bridge Rehab Pg 30 Bond/State                 $890,000   $890,000
    Pioneer Bridge   Bond/State               $325,000     $325,000
    SUBTOTAL BRIDGES
        $0 $0 $0 $0 $0 $0 $0 $960,000 $4,905,000 $540,000 $6,465,000
    TRAFFIC IMPROVEMENTS (Intersection & Calming)
    Route 2-12 Intersection Study                         $10,000
    Main/Barre St. Signal (Right Turn Lane)   CIP/IF                 $80,000 $80,000 $160,000
    River/Sherwood Signal (Right Turn Lane)   CIP/IF                   $50,000 $50,000
    Main/School Signal (Flashing Red)   CIP/IF                   $35,000 $35,000
    US 2 & Route 302 & Pioneer/River Intersection ROUNDABOUT Upgrade (Combined Project)Note FY 03 $10,000 (Local Share 5%) & 20,000Hazmat C in FY08-09   CIP/STATE $0 $25,000             $1,225,000   $1,285,000
    Traffic Calming - Study & Construction   CIP/IF $0               $4,000   $20,000
    A.Upgrade at Bailey/State Street B.Strain Poles   CIP/IF/STATE DTF           $21,000     $6,500   $43,000
    Gallison/US Route 2   CIPIF       $0 $40,000         $35,000 $75,000
    Flashing School Beacons (Solar)   CIP       $11,000             $11,000
    Overhead Sign Replacement Route 2   CIP       $38,000         $10,000   $48,000
    SUBTOTAL INTERSECTION IMPROVEMENTS
        $0 $25,000 $0 $49,000 $40,000 $21,000     $1,315,500 $200,000 $1,727,000
    RETAINING WALLS GUARDRAILS
    Sibley Avenue Slope Stability   CIP     $95,000               $95,000
    Ridge Street Slope Stability   CIP         $50,000           $50,000
    North Street Bin Wall   CIP                   $20,000 $20,000
    Hill Street   CIP   $45,000                 $45,000
    20 Sibley Avenue Wall   CIP       $20,000             $20,000
    Route 302 Rock Catchment   CIP                 $100,000   $100,000
    SUBTOTAL RETAINING WALLS GUARDRAILS
        $0 $45,000 $95,000 $20,000 $50,000 $0 $0 $0 $100,000 $20,000 $330,000
    SIDEWALK RECONSTRUCTION & RESURFACE PROGRAM ( Master Plan Pg 30, 35)
    Barre St. (Charles-Nelson)   CIP   $36,000 $36,000               $72,000
    Police Station Front   CIP                      
    College Street (E. State - Woodrow)   CIP       $30,000             $30,000
    Liberty Street   CIP     $0 $85,000           $85,000
    Berlin Street (Coordinate with Water Main Project)   CIP                     $0
    Barre (Coordinate with Street Paving Project)   CIP C   C/Bike Path               $0
    Sibley   CIP                     $20,000
    School St, Loomis, Park Ave   CIP $33,000                   $33,000
    Main Street Bank North Corner   CIP $17,000               MDCA   $17,000
    Northfield Colonial to Colonial   CIP   $0   $27,000             $27,000
    Main to Barre to Bridge   CIP   $10,000                 $10,000
    SUBTOTAL SIDEWALK RECONSTRUCTION & RESURFACE PROGRAM
        $50,000 $46,000 $36,000 $57,000 $85,000 $0 $0 $0 $0 $0 $298,000
    SIDEWALK EXTENSION PROGRAM (Master Plan pg 30, 35)
    Elm Street - Recreation Field Cost Est. for Asphalt $54,000   CIP                   $80,000 $80,000
    Hebert Road (Berlin - Isabel)   CIP     $15,000   $0   $65,000   $75,000   $155,000
    College (Hinkley - Arsenal)   CIP                   $22,000 $22,000
    Terrace Street (Jordan - Dairy) - Coordinate with Rehab   CIP                     $28,000
    Berlin Street (Hebert - Sherwood)   CIP         $0   $30,000       $30,000
    Towne Hill Road (Greenock-Westwood with Coordinate with Street Rehab)   CIP   C                 $0
    Northfield (Independence Green - Freedom Dr.)   CIP                   $50,000 $50,000
    SUBTOTAL SIDEWALK EXTENSION
        $0 $0 $15,000 $0 $0 $0 $95,000 $0 $75,000 $152,000 $365,000
    BUILDINGS & GROUNDS
    City Hall Fire Escape Maintenance   CIP                   $50,000 $50,000
    Combined Generator-Fire & City Hall   BOND               $155,000     BOND
    City Fuel Tank Replacement   BOND               $45,000     BOND
    City Hall Plaza Renovation   CIP   $3,000                 $3,000
    Police Station Secure Video   CIP $0 $5,000                 $5,000
    DPW Fuel Tank Replacement & Monitoring System   CIP               $50,000     BOND
    Fire Windows Replacement - Energy Efficient   CIP $5,500                   $33,500
    Fire - Rescue Training Tower       $7,500 $7,500               $15,000
    Fire Station Air Control Improvement       $5,000                 $5,000
    Fire-Gear Cleaning Station           $10,000             $10,000
    City Hall Electrical Wiring   BOND               $30,000     BOND
    DPW Roofs Dog River Road Replacement   CIP               $70,000     BOND
    DPW Parking Lot Resurfacing Dog River Road   CIP           $70,000         $70,000
    DPW Storage Shed Addition   BOND               $30,000     BOND
    Computer Room Improvements   CIP         $25,000 $35,000         $60,000
    Turntable Park Pg 20 State AOT & Sales Tax Reallocation $5,000               $181,000   $10,000
    SUBTOTAL BUILDINGS
        $10,500 $20,500 $7,500 $10,000 $25,000 $105,000 $0 $380,000 $181,000 $50,000 $261,500
    MISCELLANEOUS
    Hazen Place Storm Drain (Fiberglass Epoxy Liner)   CIP                   $40,000 $40,000
    Taylor Liner   CIP                   $20,000 $20,000
    Website Upgrade       $10,000                 $10,000
    City Master Plan Update   CIP/STATE $5,000 $7,500                 $42,500
    Capital Projects - Downtown Program/Blanchard Alleyway Project Enhancements for FY 05/Rite-Aid/Blanchard Sidewalks & Lighting for FY 06/Sidewalks Contribution for Langdon St Bridge & School /Main (Howard Bank area) for FY 07 Pg 35 CIP $10,000 $10,000 $10,000 $10,000 $10,000 $10,000         $100,000
    Main Street Light Poles   CIP       $14,000             $14,000
    SUBTOTAL MISCELLANEOUS
        $15,000 $27,500 $10,000 $24,000 $10,000 $10,000 $0 $0 $0 $60,000 $226,500
    SUBTOTAL ANNUAL FUNDING
        $316,378 $337,628 $310,705 $316,442 $331,819 $349,920 $366,741        
    5% Project Management     $15,819 $16,881 $15,535 $15,822 $16,591 $17,496 $18,337        
    TOTAL ANNUAL CAPITAL FUNDING
        $332,196 $354,509 $326,240 $332,264 $348,410 $367,416 $385,078        
    Change from previous year   CIP $69,497 $22,313 -$28,269 $6,024 $16,146 $19,006          
    CAPITAL DEBT
    Existing Capital Debt                          
    Berlin St Reconstruction FY12   GF $6,655 $6,337 $6,225 $5,875 $5,525 $5,175 $4,825 $140,000   $0 $212,658
    Bridges FY19   GF $54,803 $53,114 $51,399 $49,649 $47,864 $46,053 $44,224 $680,000   $219,531 $1,047,054
    Fire Station FY18   GF $61,240 $59,310 $52,474 $50,724 $48,939 $47,128 $45,299 $750,000   $243,836 $1,150,870
    Gould Hill Bridges FY10   GF $52,583 $50,179 $47,691 $25,708 $0 $0   $700,000   $0 $1,005,798
    Granite St Bridge   GF $0 $0 $0 $0       $30,000   $0 $34,705
    Library FY21   GF $52,834 $51,393 $49,934 $48,459 $46,973 $45,469 $43,938 $600,000   $337,312 $943,888
    Police Station FY21   GF $130,420 $126,817 $123,169 $119,484 $115,798 $112,008 $108,179 $1,470,000.00   $803,251 $2,299,941
    1996 Retaining Walls FY17   GF $7,782 $7,537 $7,526 $7,239 $6,948 $6,655 $6,359 $100,000   $27,902 $161,964
    1998 Retaining Walls FY19   GF $72,474 $70,480 $68,453 $66,374 $64,243 $62,067 $59,858 $925,000   $371,384 $1,399,569
    Trails   GF $0 $0 $0 $0       $55,000   $0 $61,353
    Main Street Lighting FY22   GF $16,579 $16,206 $15,818 $15,415 $15,001 $14,577 $14,141 $215,000   $132,922 $323,316
    Central VT Bike Path FY22 Pg 35 GF/State $17,960 $17,557 $17,136 $16,699 $16,251 $15,791 $15,320 $200,000 $1,800,000 $122,698 $2,098,446
    Pioneer Bridge FY24 - consider refinancing Bond Bank   Water Fund Loan Payoff               $325,000 Refinance-Bond Bank      
    City Hall, Fire & DPW Roof/Windows/Sidewalks, Electric & Standby Generator FY25   GF/STATE DTF $77,863 $76,675 $75,318 $73,831 $72,238 $70,548 $68,766 $850,000 $89,750 $698,327 $1,344,110
    Capital District Master Plan - Carr Lot BONDS TO BE SOLD IN SPRING 07 Pg 36 BOND/Federal $28,573 $28,573 $71,914 $70,614 $69,266 $67,870 $66,246 $800,000 $8,100,000 $799,158 $9,229,296
    Municipal Buildings' Alternative Heating / District Heating Pg 55 CIP/STATE OR BOND $0 $0 $7,127 $22,988 $22,707 $22,033 $23,236 $250,000 $1,150,000 $265,942 $1,490,797
    Bridges Bond, Part 1:Langdon, Memorial BP, & Refinance Pioneer & City Hall, Fire, DPW Bldg   BOND/STATE $31,539 $81,313 $79,576 $77,814 $76,025 $74,212 $72,374 $865,000 $1,140,000 $776,166 $2,409,019
    Note: April 2006 Elm St Slide Cleanup, Stabilization, Related Repairs to Elm and Cliff St Area - Funded by SIB Loan for 1.3M. This is a 3-year loan with 2.5% interest due at June 2009 maturity. State Emergency Grants will repay loan - principal & interst.   SIB LOAN/STATE $0 $0 $0 $0 $0 $0     $1,900,000 $0 $1,900,000
    Bridges Bond,Part II:Vine, Rialto & Cummings   BOND/STATE $0 $0 $0 $16,863 $43,812 $43,000 $42,157 $475,000 $2,835,000 $583,992 $687,667
    Total Proposed New Debt for March Ballot     $31,539 $0                  
    TOTAL CAPITAL DEBT
        $611,304 $645,491 $673,759 $667,736 $651,590 $632,584 $614,922 $9,105,000 $17,014,750 $5,382,421 $27,800,451
    Change from previous year     $8,004 $34,187 $28,268 -$6,023 -$16,146 -$19,006 -$17,662        
    TOTAL GENERAL FUND
        $943,500 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000        
    Target Capital Budget     $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000        
    Variance from target     -$56,500 $0 $0 $0 $0 $0 $0        

    BUDGET COMPARISON - WATER FUND


    PROJECT BY FUND MASTER PLAN Funding Source FY07 - CITY COST FY08 - CITY COST FY09 - CITY COST FY10 - CITY COST FY11-
    CITY COST
    FY12-CITY COST FY13-CITY COST BONDED AMOUNT OTHER FUNDING: Outside, CDA, Fund Balance, E-VT, etc. After FY13 - CITY COST TOTAL PROJECT COST INCLUDING FINANCING COSTS, IF APPROPRIATE
    Distribution, Transmission & Storage System (Master planPg 53)
    Hubbard St 8" (Park - East State)   Water CIP                     $142,867
    US 2 & Route 302 ROUNDABOUT 12" transmission main                         $200,000
    Streets Water CIP (See DH Report 7/2001)   Water CIP                   $7,911,644 $7,911,644
    Dickey Dam   Water CIP                   $75,000 $75,000
    Phase I Design Bailey to Granie:West Side Connector Note:$50,000 in FY03 Planning & Design   Water CIP                     $90,000
    Other Transmission & Storage Projects to be completed FY 08 & after - See DH report 7/2001   Water CIP                   $12,572,063 $12,572,063
    TOTAL DISTRIBUTION, TRANSMISSION & STORAGE
        $0 $0 $0 $0 $0         $20,558,707 $20,991,574
    Supply & Treatment System
    TOTAL SUPPLY & TREATMENT SYSTEM
        $0 $0 $0 $0 $0         $0 $0
    SUBTOTAL ANNUAL WATER CIP Not Including Reserves     $0 $0 $0 $0 $0         $20,558,707 $20,991,574
    WATER CAPITAL DEBT                          
          $0 $0 $0 $0 $0            
    West Side Connector Phase I Main St to Granite St Bridge includes sidewalks Pg 53 NEW BOND   $36,265 $90,350 $88,414 $86,469 $84,513 $82,548 $1,000,000 State $991,314 $1,459,873
    West Side Connector Phase II Northfield St to Westview Tank Pg 53 Water CIP/State               $3,700,000 State/National Life $3,700,000 $3,700,000
    River Street Route 302 to Wheelock 12" Pg 53 NEW BOND   $34,381 $88,203 $86,267 $84,332 $82,366 $80,401 $950,000 State $919,721 $1,375,661
                               
    Town Hill Water System (Lease)FY25 Pg 53 Operating Budget $36,000 $36,000 $36,000 $36,000 $36,000 $36,000 $36,000     $432,000 $720,000
    Water Tower Terrace St FY08 Pg 53 Water CIP $128,316 $124,501 $0 $0 $0 $0 $0     $0 $2,134,418
    Water Filtration PlantFY21 Pg 53 Water CIP $197,483 $202,608 $209,331 $208,206 $206,731 $204,906 $203,081 $2,495,000   $1,710,093 $5,602,528
    Water Filtration Plant FY 25 Pg 53 FED/STATE $318,937 $318,276 $321,139 $321,210 $320,722 $319,699 $318,676 $4,150,000 CITY COSTS ONLY $4,187,894 $6,501,830
    Westside Connector Bailey Ave:State -Memorial; Bailey to Taylor to Main FY25 Pg 53 Water CIP $108,656 $106,729 $105,016 $109,426 $107,539 $110,532 $107,539 $1,400,000   $1,412,904 $2,194,775
    SUBTOTAL WATER CAPITAL DEBT     $789,392 $858,760 $850,039 $849,523 $841,793 $838,016 $828,245     $12,502,950 $20,902,190
    TOTAL WATER FUND
        $789,392 $858,760 $850,039 $849,523 $841,793 $838,016 $828,245     $33,061,657 $41,893,764
    Target Capital Budget     $780,000 $780,000 $780,000 $780,000 $780,000 $780,000 $780,000        
    Variance from Target     $9,392 $78,760 $70,039 $69,523 $61,793 $58,016 $48,245        


    BUDGET COMPARISON - SEWER FUND
    PROJECT BY FUND MASTER PLAN Funding Source FY07 - CITY COST FY08 - CITY COST FY09 - CITY COST FY10 - CITY COST FY11-
    CITY COST
    FY12-CITY COST FY13-CITY COST BONDED AMOUNT OTHER FUNDING: Outside, CDA, Fund Balance, E-VT, etc. After FY13 - CITY COST TOTAL PROJECT COST INCLUDING FINANCING COSTS, IF APPROPRIATE
    Wastewater Treatment
          $0           $360,000      
    SUBTOTAL WASTEWATER TREATMENT     $0 $0 $0 $0 $0 $0 $0 $360,000   $0 $0
    Collector & Interceptor Systems                          
    Emergency Electrical Systems Collection System FY 04 $25,000   Sewer CIP                     $50,000
    SUBTOTAL COLLECTOR & INTERCEPTOR SYSTEMS     $0 $0 $0 $0 $0 $0 $0     $0 $50,000
    SUBTOTAL ANNUAL WASTEWATER CIP
        $0 $0 $0 $0 $0 $0 $0     $0 $50,000
    CAPITAL DEBT
    CSO Phase I - Local Share Bond FY16     $46,690 $45,219 $45,159 $43,433 $41,688 $39,927 $38,152 $600,000   $167,416 $971,784
    CSO RF1 021 FY16     $22,049 $22,049 $22,049 $22,049 $22,049 $22,049 $22,049 $440,432   $110,245 $440,432
    CSO RF1 027 FY17     $38,856 $38,856 $38,856 $38,856 $38,856 $38,856 $38,856 $777,110   $233,136 $777,110
    CSO RF1 028 FY18     $14,156 $14,156 $14,156 $14,156 $14,156 $14,156 $14,156 $289,812   $99,092 $289,812
    CSO RF1 047 FY20     $35,497 $35,497 $35,497 $35,497 $35,497 $35,497 $35,497 $707,693   $283,976 $707,693
    CSO Phase II - Local Share Bond FY31     $87,111 $85,559 $83,940 $82,261 $80,535 $78,769 $76,955 $1,140,000   $1,078,993 $2,020,466
    CSO RF1 059 FY22     $13,255 $13,807 $13,255 $13,255 $13,255 $13,255 $13,807 $265,100   $138,070 $265,096
    CSO RF1 068 FY22     $26,294 $26,294 $26,294 $26,294 $26,294 $26,294 $26,294 $525,880   $289,234 $525,880
    CSO RF1 071 FY23     $33,750 $34,400 $33,750 $33,750 $33,750 $33,750 $34,400 $675,000   $371,250 $675,000
    CSO RF1 02-8 FY25     $25,785 $25,785 $25,785 $25,785 $25,785 $25,785 $26,064 $515,705   $335,209 $515,705
    CSO RF1 03-9     $28,232 $28,232 $28,232 $28,232 $28,232 $28,232 $22,436 $564,646   $367,016 $564,646
    CSO RF1 03-10     $6,197 $4,483 $6,197 $6,197 $0 $0 $0 $123,940   $80,561 $123,940
    WWTP Improvements - 1988 Refinanced '92 FY08     $14,510 $13,757 $13,005 $0 $0 $0   $200,000   $0 $316,236
    I. WWTP Improvements RF1 033 FY24     $182,371 $174,171 $174,171 $174,171 $174,171 $174,171 $174,171 $3,647,420   $2,264,223 $3,647,420
    Ultraviolet Disinfection System and Emergency Power     $74,000 $74,000 $74,000 $74,000       $1,480,000   $1,110,000 $1,480,000
    Ultraviolet Disinfection System FY25     $116,708 $114,588 $113,804 $112,055 $115,169 $117,979 $114,150 $1,480,000   $1,474,660 $2,308,402
    Screw Pumps Bond 15 yr   NEW BOND   $12,780 $39,077 $38,109 $37,136 $36,159 $35,176 $360,000   $281,931 $480,368
    River Street Sewer Bond 20 yr   NEW BOND     $14,506 $36,140 $35,366 $34,588 $33,805 $400,000   $429,544 $583,949
    SUBTOTAL LONG TERM DEBT
        $691,461 $689,634 $727,733 $730,240 $721,938 $719,467 $705,968 $12,712,738 $0 $8,004,556 $11,841,221
    TOTAL SEWER FUND
        $691,461 $689,634 $727,733 $730,240 $721,938 $719,467 $705,968     $8,004,556 $11,941,221


    BUDGET COMPARISON -
    Parking Projects, Cemetery Fund, Parks Fund


    PROJECT BY FUND MASTER PLAN Funding Source FY07 - CITY COST FY08 - CITY COST FY09 - CITY COST FY10 - CITY COST FY11-
    CITY COST
    FY12-CITY COST FY13-CITY COST BONDED AMOUNT OTHER FUNDING: Outside, CDA, Fund Balance, E-VT, etc. After FY13 - CITY COST TOTAL PROJECT COST INCLUDING FINANCING COSTS, IF APPROPRIATE
    PARKING PROJECTS
    Carr Lot Replacement Parking (Parking Garage) Pg 36 Bond/Private   C   $1,110,000       $1,110,000 $10,013,911   $11,123,911
    Carr Lot Transit & Welcome Center (In addition to previously approved $800,000 Bond) Pg 36             $1,100,000   $1,100,000 $9,049,305   $10,149,305
    Parking Lot Resurface Pg 36     $42,000 $39,000               $81,000
    Notes for Parking Lot Resurface Pg 36     Blanchard Lot Pitkin Lot                
    Parking Lot Improvement Amenities Pg 36     $10,000 $10,000               $20,000
    TOTAL PARKING FUND
        $0 $52,000 $49,000 $1,110,000 $0 $1,100,000 $0       $2,366,000
    CEMETERY FUND PROJECTS
    Roads including drainage   GF $3,000 $6,000 $6,000 $6,000 $7,000 $7,000         $51,000
    Chapel Work Plan   GF                     $5,000
    Restoration Monuments   GF $2,000   $4,000 $4,000 $4,000 $4,000         $28,500
    New Roof for Toolshed   GF $3,000                   $8,000
    New Developments/West End Development/Columbarium   GF $3,000 $5,000 $6,000 $6,000 $6,000 $6,000         $49,000
    Elm Street Cemetery   GF                     $500
    CEMETERY FUND TOTAL
        $11,000 $11,000 $16,000 $16,000 $17,000 $17,000 $0       $142,000
    PARKS FUND PROJECTS
    Tower Stairs   GF CIP $7,000 $7,000 $10,000               $24,000
    Outhouse Replacement   GF/Park Impact Fees     $1,000 $1,000              
    Entrance Gate   GF/Park Impact Fees       $5,000 $5,000 $5,000          
    Toolshed Winterizing   GF/Park Impact Fees   $2,750                  
    PARKS FUND TOTAL
        $7,000 $9,750 $11,000 $6,000 $5,000 $5,000 $0       $43,750


    BUDGET COMPARISON -
    SUMMARY BY FUND

    PROJECT BY FUND MASTER PLAN Funding Source FY07 - CITY COST FY08 - CITY COST FY09 - CITY COST FY10 - CITY COST FY11-
    CITY COST
    FY12-CITY COST FY13-CITY COST BONDED AMOUNT OTHER FUNDING: Outside, CDA, Fund Balance, E-VT, etc. After FY13 - CITY COST TOTAL PROJECT COST INCLUDING FINANCING COSTS, IF APPROPRIATE
    GENERAL FUND
        $943,500 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000 $1,000,000        
    WATER FUND
        $789,392 $858,760 $850,039 $849,523 $841,793 $838,016 $828,245        
    SEWER FUND
        $691,461 $689,634 $727,733 $730,240 $721,938 $719,467 $705,968        
    PARKING FUND
        $0 $52,000 $49,000 $1,110,000 $0 $1,100,000 $0        
    CEMETERY FUND
        $11,000 $11,000 $16,000 $16,000 $17,000 $17,000 $0        
    PARKS FUND
        $7,000 $9,750 $11,000 $6,000 $5,000 $5,000 $0        
    TOTAL ALL FUNDS
        $2,435,353 $2,611,394 $2,642,772 $3,705,763 $2,580,731 $3,674,484 $2,534,213        

     
    back to top
    For More Information
    Sandra Gallup, Finance Director
    City of Montpelier
    39 Main Street, City Hall
    Montpelier, VT 05062-2950
    (802) 223-9514
    sgallup@montpelier-vt.org
    http://www.montpelier-vt.org/finance
      William Fraser, City Manager
    City of Montpelier
    39 Main Street, City Hall
    Montpelier, VT 05062-2950
    (802) 223-9502
    wfraser@montpelier-vt.org
    http://www.montpelier-vt.org/manager



    Updated February 9, 2007

    Please send comments to: webmaster@montpelier-vt.org

    Copyright © 1998-2008 City of Montpelier, Vermont.
    Hosted by http://www.networksolutions.com