Project Title:
Taylor Street Bridge Project
Vermont Agency of Transportation Project Number: BHF 6400(31)
Project Description:
Rehabilitation of BR5 located on Taylor Street in Montpelier and crossing over the Winooski River serving as a connection between State Street (Bus Rte 2) on the north side of the river to Memorial Drive (US Rte 2) on the south side. Project consists of the rehabilitation of the superstructure, substructure repairs and reconstruction of the approaches, replacement of the deck surface, railings and guardrails, reconstruction of the roadway approaches, and replacement of the bridge suspended municipal water main.
Special Project Note: Bridge to be closed during construction. Temporary traffic control during bridge closure to consist of a traffic signal installed at the intersection of Taylor St / Governor Davis Avenue / State Street for peak traffic time operation.
Existing Condition:
The bridge is a steel “Parker” through truss constructed in 1929. It is located in the Montpelier Historic District and listed on the National Register of Historic Places. Project is eligible for federal historic preservation funding assistance.
Project Manager:
Susan E. Scribner
Vermont Agency of Transportation
Project General Contractor:
Winterset, Inc.
Lyndonville, VT
Project Cost / Funding Split:
Estimated Total Construction Cost: $1,746,921
Funding: 100% Federal, 0% State, 0% Local |
Project Resident Engineer:
Robert E. Suckert
Vermont Agency of Transportation
Construction Division
828-2593
Municipal Contact:
Todd Law, P.E.
City of Montpelier
Public Works Director
|
Project Schedule (as submitted by contractor):
December, 2009 – November 12, 2010
Contractor Mobilization: week of January 11th
Installation of temporary traffic signal @ Taylor / State intersection: week of January 18th
Bridge Closure & implement traffic detour: approximately February 1st
Bridge painting: week of August 23rd
Bridge & street reopening: week of October 27th
|
|
September 01, 2010
Glenn Nicholson Leaves Fire Dept After 62 Years of Service
Read Full Story
|
January 21, 2010
Montpelier Wins $8 Million Federal Energy Grant
Read Full Story
|
December 11, 2009
City To Be Paid In Full In Scott Construction Matter
Read Full Story
|
Sep 06, 2010 All Day
Holiday - City Offices Closed
City offices will be closed in observation of Labor Day.
More
|
Sep 07, 2010 3:00 pm
Finance Sub-Committee Meeting
More
|
Sep 07, 2010 4:30 pm
Senior Services Coordinating Committee Meeting
More
|
Community Justice Center Position Available - Reentry Specialist
Read Notice
|
Historic Preservation Commission Vacancies
Read Notice
|
Design Review Committee Vacancies
Read Notice
|
|
|