The State House
Home

About Montpelier

Area Attractions
& Things to Do


Doing Business
in Montpelier


Getting Here
& Getting Around


City
Departments
& Services


Boards
& Commissions


Other Services
& Organizations


Calendar of Events

News & Weather

Notices -
Jobs - Bids


WHAT'S NEW


Works in
Progress
 < 

Document Library

U.S.S. Montpelier
Museum



Search the site...

Berlin & River Streets
Water Improvements Project
to main Works in Progress page
Berlin & River Streets Water Transmission Main Project subsection links
Background  |  Project Timeline  |  Meetings  |  Contact Information

...back to top
Background

River Street
Water: This project is necessary to provide a reliable source of water along River Street and on the Barre-Montpelier Road. Prior to this upgrade, adequate fire protection could not be provided along River Street due to the undersized lines. The new River Street water main connects to the Route 2/302 main that was installed in 2005.

Sewer: The portion of the sewer on River Street that will be replaced is 12” diameter clay tile pipe. There is an 18” diameter reinforced concrete pipe that connects to this line on both the upstream and downstream sides. It is one of the oldest mainline sewers in the City and is undersized for the volume of flow it takes from both the Montpelier and the Berlin pump stations. The occasional odors present in this area have been attributed to this portion of the sewer becoming air locked.

Berlin Street
A 16” water main was installed several years ago to the bottom of Berlin Hill and extends to the Montpelier Water Treatment Facility. This main was connected to the existing 8” water main near Granite Street. By extending the new 16” line to where the Memorial Drive water project ended in 2004 near School Avenue, a reliable and sufficient flow of water can be provided to the Downtown and Northfield Street area.

In addition to the capacity upgrades needed, the existing water mains were in very poor condition. They were installed sometime in the 1940’s and the Cities crews have had to repair multiple breaks in the line over the past few years.

Why Now -
The City is pushing to complete these projects this year because a large State paving project is scheduled to take place in the summer of 2009. In addition, the reconstruction of the Route 2 / Route 302 intersection is planned to start towards the end of this summer and continue into 2009. By having these infrastructure improvements completed this summer, the trenches required to install the utilities will have time to settle over the next year and the new pavement will last longer. Paving is an expensive portion of roadway maintenance and repairing aging and undersized utilities ahead of full width roadway surfacing is economical management.

...back to top
Project Timeline
Description Duration Early Start Early Finish
Berlin Street 90 days 5/13/08 9/15/08
Mobilization- Berlin St. 4 days 5/13/08 5/16/08
Connection -0+00
1 day 5/19/08 5/19/08
16" Water Main-0+00-7+00 6 days 5/20/08 5/27/08
Test/Chlorinate-7+00 7 days 5/28/08 6/5/08
Water Services (7) -7+00 4 days 6/6/08 6/11/08
Curbing/Sidewalk-7+00 10 days 6/9/08 6/20/08
16" Water Main 7+01-14+60 7 days 5/28/08 6/5/08
Test/Chlorinate-7+01-14+60 7 days 6/6/08 6/16/08
Interconnection 13+90 1 day 6/17/08 6/17/08
Water Services (10) 7+01-14+60 5 days 6/17/08 6/23/08
Curbing/Sidewalk 7+01-14+60 12 days 6/25/08 7/11/08
16" Water Main 14+61-23+00 14 days 6/6/08 6/25/08
Connection 23+00 1 day 6/26/08 6/26/08
Test/Chlorinate 14+61-23+00 7 days 6/27/08 7/8/08
Water Services (12) 14+61-23+00 10 days 7/9/08 7/22/08
Curbing/Sidewalk 14+61-23+00 15 days 7/24/08 8/13/08
Cut/Caps Sta 0+00, 23+00 1 day 7/23/08 7/23/08
Permanent Pavement 40 days 7/14/08 9/5/08
Misc. Work & Cleanup 82 days 5/19/08 9/10/08
Demobilization 3 days 9/11/08 9/15/08
River Street 188 days 9/18/07 6/5/08
Mobilization - River Street - DONE 10 days 9/18/07 10/1/07
Interconnection - 50+00 - DONE 1 day 10/1/07 10/1/07
12" Water Main - 50+00-66+95.9 - DONE 15 days 10/1/07 10/19/07
Interconnection - 66+95.9 - DONE 1 day 10/22/07 10/23/07
12" Water Main Ext. - 67+00 - Wheelock - DONE 8 days 10/24/07 10/29/07
8" Bore - 66+10 Scribner St. - DONE 1 day 11/12/07 11/12/07
Scribner St. Interconnection - phase 1 - DONE 2 days 11/26/07 11/27/07
Test/Chlorinate - DONE 7 days 11/21/07 11/29/07
Scribner St. Final Connection - DONE 1 day 12/4/07 12/7/07
4" Bore - 63+30 - DONE 1 day 11/8/07 11/8/07
8" Bore - 61+65 Taplin St. - DONE 1 day 11/2/07 11/6/07
Taplin St. Interconnection - DONE 1 day 11/27/07 11/28/07
6" Bore - 60+08 - DONE 2 days 11/1/07 11/2/07
8" Bore- 59+10 Blackwell St - DONE 2 days 10/31/07 11/1/07
Blackwell St. Interconnection - DONE 1 day 11/22/07 11/22/07
4" Bore - 56+20 - DONE 1 day 10/31/07 10/31/07
Water Services 50+00 - Scribner St. - DONE 5 days 11/15/07 12/7/07
Wheelock St. - Interconnection - DONE 1 day 11/26/07 11/26/07
Misc Work/Cleanup - 2007 - DONE 13 days 11/16/07 12/7/08
Permanent Paving - 2007 - DONE 8 days 11/13/07 11/21/07
Prep for Winter Shutdown - DONE 2 days 12/10/07 12/11/07
Winter Shutdown 97 days 12/12/07 4/28/08
4" Bore - Scribner-Wheelock 4 days 4/29/08 5/2/08
Water Services - Scribner-Wheelock 5 days 4/29/08 5/5/08
Permanent Pavement - Sta 55+00 - Wheelock 20 days 5/6/08 6/2/08
Misc Work/Cleanup - 2008 29 days 4/28/08 6/5/08

...back to top
Meetings
Below are copies of the meeting schedule and notes from recent meetings.
The latest, free version of Adobe Acrobat Reader is available HERE.
Meeting Schedule  - 2 pages, 285 KB
Construction Schedule  - 2 pages, 300 KB
Meeting Minutes - April 2, 2008  - 6 pages, 38 KB
Meeting Minutes - April 18, 2008  - 5 pages, 22 KB


back to top
For More Information
  Department of Public Works
Montpelier City Hall
39 Main Street
Montpelier, VT 05602-2950
Phone: (802) 223-9508
FAX:(802) 223-9524

Administration
Todd Law, Director of Public Works, tlaw@montpelier-vt.org
Thomas McArdle, Assistant Public Works Director, tmcardle@montpelier-vt.org
Ginny Mackey, Administrative Assistant, gmackey@montpelier-vt.org


Updated April 28, 2008
 
Please send comments to: webmaster@montpelier-vt.org

Copyright © 1998-2008 City of Montpelier, Vermont.
Hosted by http://www.networksolutions.com