|
|
US Route 2/302
Intersection Improvements
Evaluation of Alternatives
After holding both local and regional concerns meetings, an exhaustive list of alternatives
was developed and examined by a study committee comprised of the City, CVRPC and adjacent
landowner representatives. Due to the large number of commercial and residential driveways
in close proximity to the intersection, special consideration was taken as part of the
design improvement alternatives. Once a list of alternatives was created the committee
then decided on the three most feasible alternatives.
Alternative Evaluation Matrix
| |
DO-NOTHING
3-WAY
(Optimized Signal Timings) |
SIGNALIZED
4-WAY
(Protected + Permitted Phasing) |
ROUNDABOUT
5-WAY
(One Lane) |
| Preliminary
Cost Estimate |
$0 |
$845,000 |
$825,000 |
| Maintenance
and Operational Costs |
$1,150 / year (signal
related) |
$2,500 / year (signal
related) Slightly higher than existing plowing costs due to additional turning
lanes. |
$0 per year (signal related)
Moderately higher than existing snow plowing costs, use of loader may be required
to remove snow. |
| Accident
Costs |
$316,300 per year |
$241,700 per year |
$178,200 per year |
| User
Delay (2015 PM Peak Hour) |
4,976 vehicle minutes
per hour (Signal 97) |
11,857 vehicle minutes
per hour (Signal 97) |
1,428 vehicle minutes
per hour (SIDRA) 1,222 vehicle minutes per hour (RODEL) |
| Energy
Consumption |
26.4 gallons per hour*
(signalized movements only) |
142.3 gallons per hour |
49.4 gallons per hour |
| Air
Pollution (2015 PM Peak Hour) |
26.7 kg CO Em per hour
(signalized movements only) |
301.2 kg CO Em per hour |
34.2 kg CO Em per hour |
| Lighting |
No intersection lighting
exists |
Two new pole mounted metal
halide fixtures |
Three new metal halide
fixtures mounted on free standing poles |
| Hydraulics |
Existing pavement area
= 73,400 square feet |
New pavement area = 68,000
square feet |
New pavement area = 64,250
square feet |
| Total
Disturbance |
0 Acres |
2.27 Acres |
2.23 Acres |
| * Energy Consumption
and Air Pollution estimates for the do-nothing alternative include signalized
movments only. Vehicles using the eastbound right-turn lane on US Route 2 and
using the crossover area between US Route 2 and US 302 are not included. |
A five-leg roundabout was chosen by the Montpelier City Council, the Central
Vermont Regional Transportation Agency Committee and the Project Study Committee and
was approved by the VTrans Project Development Team as the preferred alternative.
The proposed roundabout included two approaches for Route 2, one for Route 302,
one for Walker Motors and one for the Grossman parcel. The intersection would
be initially constructed as a single-lane roundabout designed to accommodate
the largest permitted truck. The roundabout would also be designed such that it
could be expanded to a two-lane roundabout in the future if necessary with
minimal changes. This alternative was chosen because it has the potential to
meet all the goals of the study conducted. More specifically the scoping study
indicates that:
- The occurrence of injury and fatality accidents at a roundabout is lower than at a
signalized or stop sign or controlled intersection;
- Both the Walker Motors and Grossman parcel approaches would be safer than their
existing access points;
- Due to the geometry of the approaches, there would be room for Irving Oil to install
an exclusive left-turn land on US Route 302 if needed for any proposed development
on their site;
- Shorter queues are anticipated on US Route 2 with the roundabout alternatives, which
creates less potential for driveway obstruction;
- There would be room across the Winooski River bridge for a sidewalk to connect the
Winooski East Path with the with the roundabout alternative;
- There would be room for a sidewalk and bike lanes from Pioneer Street to the
intersection (3 lanes become two on US Route 2 leaving room for the sidewalk and bike
lanes); and
- A roundabout would provide a traffic calming effect and would serve as a gateway to
slow traffic entering Montpelier.
The total design / construction cost estimate for this project is $1,025,000
(including $825,000 for the roundabout and $200,000 for the US Route 2 approach work
from Pioneer Street to US Route 302).
For More Information
Lamoureux & Dickinson
Jody Carriere
14 Morse Drive
Essex Junction, VT 05452
(802) 878-4450
Jody@LDengineering.com
|
|
City of Montpelier
Public Works Department
Tom McArdle
39 Main Street, City Hall
Montpelier, VT 05062-2950
(802) 223-9508
tmcardle@montpelier-vt.org
|
Updated August 8, 2005
|