Schedule & Scope of Work
Step I - Issue Identification & Preliminary Assessment
- Data gathering
- Public Meeting 1 - June 5, 2003, 7:00-9:00 p.m., City Hall
- Identify issues and concerns of the general public, business owners, and property owners
- Develop conceptual parking garage footprints at each site
- Evaluate sites:
- Potential Parking Garage Impacts:
- Vehicle access and circulation
- Pedestrian access and circulation
- Safety and security
- Truck access and delivery
- Emergency vehicle access and operations
- Vehicle and pedestrian access to surrounding buildings
- Aesthetics of the surrounding area
- Utilities
- Flood plain and permitting issues
- Traffic congestion on the surrounding street network
- Other issues as identified by the public
- Potential net increase in parking spaces
- Performance Measures:
- Positive impact
- No impact
- Low negative impact
- Severe negative impact
- Potential Parking Garage Impacts:
- Public Meeting #2 - Parking Committee - September 29, 2003
- Study amended to include review of collaborative effort with Duane Wells, a neighboring property owner.
- Go/No go decision based on preliminary assessment and public input
- Prepare conceptual footprints, elevations, and cross sections
- Prepare order of magnitude capital and operating costs
- Review findings with City officials
- Public Meeting #3 - Parking Committee
- Public Meeting #4 - present findings to City Council
- Summarizes all previous work; includes executive summary
- Identifies next steps and cost of design and engineering for parking structures (if recommended)