- Spring 2008
- Final plans submitted in April, 2008 allowing for 1 month to complete final review
- Environmental permits updated and resolved
- Request for Qualifications to perform construction inspection services released for advertisement and due May 8, award contract 3rd week of May.
- Anticipate VTrans approval of plans, specification and cost estimate (PSE) by May 1st
- Advertise for construction by end of May, award construction contract first week of July and construction anticipated to begin by approximately 3 week of July (final completion October, 2009)
- February 2008 - R.O.W. clearance certificate issued by VTrans. All property rights and agreements necessary to construct the project have been secured. Final design authorized for completion
- 2007 - Congress approved 100% federal funding for roundabout projects because of significant safety and efficiency benefits. Local share at 5% for preliminary engineering previous to funding change
- Spring 2005
- Permitting and environmental documents completed
- R.O.W. funding allocated and authorized to commence May 2005
- The project is in the preliminary final planning stage, and is at 85% completion
- Right-of-way plans are complete. Erosion control plans are complete.
- Funding will be 95% Federal $$, 0% State $$, 5% local $$
- May 2003 - City hired Lamoureux and Dickinson as consulting engineers to perform design services
- January 2003 - City hired Bob Merchant as its Municipal Project Manager (P.E., Marcon Corp) to assist with project development
- August 2002 - City obtained approval from VTrans to undertake the project through the Local Transportation Facilities (LTF) program. Montpelier entered into a Cooperative Agreement (CA) with VTrans for funding and assistance through this program
- August 2001 - Final Scoping Report approved
- June 2001 - VTrans Project Definition Team reviewed pre-scoping report